Tokyo Electric Power Company Holdings is reviewing the August 2029 completion plan for a mandatory anti-terrorism facility at its Kashiwazaki-Kariwa Unit 7 reactor, a setback expected to further delay the reactor’s restart. Tepco announced the review on November 26, according to Jiji reporting published by The Japan Times. Source
The contractor told Tepco that construction needs more than an additional year, citing factors including labor shortages, the utility said. No revised completion target has been set. Source
Plant manager Takeyuki Inagaki told a news conference: “We would like to aim for completion in April 2031,” according to NucNet. That is a facility-completion aim, not a firm construction schedule or a promised reactor restart date. Source Source
Bloomberg separately reported a problem with the strength of concrete used in the mandatory structure. Source
An already-revised plan needs another revision
The facility’s earlier completion deadline was October 2025. Tepco subsequently pushed completion back to August 2029 as regulatory reviews for the reactor’s restart took longer than expected, Jiji reported. The company opted to restart Unit 6 before Unit 7. Source
The requirement comes from Japan’s safety standards introduced after the March 2011 Fukushima disaster. Those rules require anti-terrorism facilities within five years of approval of reactor construction plans, according to Jiji. Source
Unit 6 restarted in January 2026, but its own anti-terrorism facility also remains unfinished. It will be unable to continue operating unless that facility is completed by April 2031, Jiji reported. Getting back online does not make the construction deadline disappear. Source