Google has acquired Crusoe’s data-center site in southeast Wyoming, Crusoe said on November 6, a day after Google announced plans to invest $17 billion in the project. The acquisition’s financial terms weren’t disclosed. That $17 billion is for development, not a very expensive receipt for the site. Source Source
Crusoe said it has completed its pre-development involvement, which covered site selection, government approvals and power strategy. The campus was initially developed by Crusoe and Tallgrass Energy. Google says it will build what would be its first Wyoming data center with Tallgrass, Black Hills Energy, American Electric Power and Related Digital. Source
The power supply is a project, too
The facility is in Laramie County and is intended to power AI tasks, according to Silicon UK’s account of Google’s announcement. Some of its electricity would come from a planned 702-megawatt fuel-cell development, with Bloom Energy set to supply the fuel cells. The cloud requires rather more than a spare wall socket. Source
That 702-megawatt figure describes generation capacity for the fuel-cell development, not the data center’s total capacity or electricity already being delivered to servers. Source
Google also said it would pay for all the power the data center uses, Silicon UK reports. That promise doesn’t establish who would cover other potential project costs. Source
This handover isn’t a Google–Crusoe breakup. Crusoe said it is developing another Google data-center campus in Armstrong, which it announced earlier this year. Source