NTPC terminates GR Infraprojects contract for 400-MWh battery storage project
Businessline reports that contractor defaults and project delays prompted the termination. The project is at Mouda Super Thermal Power Station in Maharashtra.
TLDR
State-run NTPC announced on September 19 that it had terminated GR Infraprojects’ contract for a 400-MWh battery energy storage system at Mouda Super Thermal Power Station in Maharashtra, Businessline reports. The report cites contractor defaults and project delays as the reasons.
Combined views
1.1K
1 Source, first seen 1d ago
NTPC terminates GR Infraprojects contract for 400-MWh battery storage project
Businessline reports that contractor defaults and project delays prompted the termination. The project is at Mouda Super Thermal Power Station in Maharashtra.
TLDR
State-run NTPC announced on September 19 that it had terminated GR Infraprojects’ contract for a 400-MWh battery energy storage system at Mouda Super Thermal Power Station in Maharashtra, Businessline reports. The report cites contractor defaults and project delays as the reasons.