US power-line construction slows as AI drives up electricity demand
US high-voltage line construction fell from nearly 4,000 miles in 2013 to fewer than 900 in 2024.
TLDR
A 102-mile transmission line between Iowa and Wisconsin took nearly 13 years from grid-operator approval to operation, amid disputes over its route and overlapping rules. Grid Strategies projects US electricity demand will rise by 166 gigawatts by 2030. Grid operators can identify needed lines but cannot compel companies to build them.