Oracle said on November 20, 2026, that it had secured all the funding needed to fulfill its OpenAI infrastructure contract after its final capital raise earlier in the month. Source
Reuters reports that Oracle announced a $20 billion raise earlier in the month, comprising about $10 billion in stock and $10 billion in debt. That figure describes the raise, not the total value of the OpenAI contract. The announcement follows investor scrutiny of Oracle’s AI data-center expansion costs and growing exposure to OpenAI. Source
“The financing we outlined at Oracle Investor Day, including vendor financing, is in place,” Oracle said. It called further private vendor discussions “additional options,” adding: “Our ability to deliver on our OpenAI contract does not depend on those discussions.” Source
Oracle shares rose as much as 3.3% in after-hours trading, according to Reuters. Source
Texas campuses and cash-flow targets
Oracle and OpenAI aim to develop 4.5 gigawatts of additional US data-center capacity beyond the initial Stargate site in Abilene, Texas, Reuters reports. Source
Oracle says its Abilene campus is nearly complete. Its next gigawatt-scale campus, in Shackelford County, Texas, is fully permitted, and the company says handover of Nvidia Vera Rubin racks there is on track for the coming weeks. A permit isn’t a power switch. Source Source
Oracle expects positive free cash flow, meaning cash left from operations after capital spending, in the second half of fiscal 2028. The company targets more than $30 billion in free cash flow in fiscal 2029 and expects to pay for future growth with its own cash beginning that year. Source