Texas freezes new data center permits amid a surging grid queue

a16z says Texas’ large-load queue reached 474 GW by June; just 9.5 GW was approved and 4.3 GW running.

a16zA1
2 Sources, 1h ago, first seen 1h ago

TLDR

a16z says Texas froze new data center permits after its large-load grid queue grew from 63 GW at the end of 2024 to 474 GW by June 2026, about 90% of it data centers. Its analysis argues that duplicate and speculative requests make it harder to plan grid upgrades without leaving ratepayers to cover costs for projects that never materialize. It urges Texas to exempt projects that have funded their first phase and generators permitted only for emergencies.

Combined views

20.2K

2 Sources, first seen 1h ago

136 likes26 comments78 saves25 reposts

Combined views

20.2K

2 Sources, first seen 1h ago

136 likes26 comments78 saves25 reposts

Sentiment

Positive——Negative

Summary

Not enough discussion yet.

No sentiment analysis available yet.

Featured Source

Sentiment

Positive——Negative

Summary

Not enough discussion yet.

No sentiment analysis available yet.

2 Sources

a16z@a16zTexas just froze new data center permits: - Its queue went from 63 GW to 474 GW in 18 months, more than 5x record peak demand - Only 9.5 GW is approved and about 4.3 GW is actually running - The rest is duplicates, speculation, and developers who have never plugged in a GPU a16z's @rmcentush on why the grid can't build for that many maybes: https://www.a16z.news/p/why-texas-is-making-data-centers1h
    • Home
    • Technology
    • Gaming
    • Entertainment
    • World & Business
    • Science
    • Sports
    • AI

    2 Sources

    a16z@a16zTexas just froze new data center permits: - Its queue went from 63 GW to 474 GW in 18 months, more than 5x record peak demand - Only 9.5 GW is approved and about 4.3 GW is actually running - The rest is duplicates, speculation, and developers who have never plugged in a GPU a16z's @rmcentush on why the grid can't build for that many maybes: https://www.a16z.news/p/why-texas-is-making-data-centers1h
    Today's Rank

    #14

    Today's Rank

    #14